
blindman river stabilization & filtration project
1976 to present
A Project That Has Protected Gull Lake for Nearly 50 Years:
Since 1976, controlled pumping from the Blindman River has played a critical role in stabilizing Gull Lake during periods of severe decline. In 2018, pumping was voluntarily suspended to prevent the potential transfer of invasive Prussian carp and their eggs into the lake.
What followed was not a pause. It was a transformation.
Over the decades, dedicated volunteers and past board members invested thousands of hours advancing research, regulatory coordination, and technical planning to protect Gull Lake’s future.
Their persistence laid the groundwork for the engineered solution now moving forward.
From Concept to Engineered Infrastructure:
Beginning in 2022, GLWS initiated a detailed investigation into pressurized filtration systems capable of preventing carp egg transfer while maintaining pumping capacity.
Two filtration technologies were pilot-tested under real pumping pressures. Testing demonstrated:
-
Successful operation at 1,000 USGPM
-
Filtration down to 200 microns
-
Carp eggs averaging approximately 1,000 microns
-
Independent oversight from provincial departments, municipalities, and engineering consultants
Engineering review by Stantec concluded that:
“A properly designed pressurized filtration system with failure mitigation will be
100% successful in preventing carp eggs from entering Gull Lake.”
That foundation gave the project confidence. But it did not stop there.
Engineering Enhancements:
When detailed design advanced under MPE Engineering Ltd., the project evolved significantly beyond the original conceptual scope.
The finalized design now includes:
-
A two-stage filtration system for layered protection
-
Expanded structural works
-
Significant concrete infrastructure upgrades
-
An elegant expansion to the existing pumphouse
-
Modernized operational controls
The expanded design is intended to deliver a more robust, durable, and future-ready facility than originally envisioned.
This is not a retrofit. It is a generational infrastructure upgrade.
Provincial Procurement Process:
The Blindman River Stabilization and Filtration Project has progressed through provincial engineering, regulatory, and procurement processes.
The expanded scope of the project includes filtration equipment, structural improvements, and upgrades to the existing pumphouse. These improvements are intended to provide long-term protection against the introduction of invasive Prussian carp and their eggs into Gull Lake.
The project has required coordination among provincial departments, engineering consultants, and other stakeholders.
Although the procurement and construction processes have taken longer than originally anticipated, the objective remains unchanged: to restore a safe and reliable means of transferring water from the Blindman River into Gull Lake when conditions permit.
GLWS continues to follow the project's progress and will share confirmed developments as information becomes available.
Government Support:
In spring 2025, GLWS Board members met with:
-
Danielle Smith
-
Rebecca Schulz
-
RJ Sigurdson
Their engagement and support signaled strong provincial alignment on the importance of stabilizing Gull Lake.
The project has since progressed within formal government infrastructure channels.
Current Lake Conditions:
Gull Lake continues to experience exceptionally low water levels, creating significant challenges for shoreline property owners, recreational users, and the surrounding communities.
Low water levels have affected access to boat launches, increased the distance between established shorelines and the water's edge, and created uncertainty for residents who depend on adequate water depths for seasonal boating.
The established lake-level target is 899.16 metres above sea level.
As of November 1, 2026, Gull Lake's recorded water level was 897.922 metres above sea level — approximately 1.24 metres (4.06 feet) below the established target level.
This measurement illustrates the seriousness of Gull Lake's declining water levels and reinforces the importance of restoring a reliable, long-term means of stabilizing the lake.
While natural precipitation and evaporation influence Gull Lake's water levels, the Blindman River pumping system has historically provided an additional means of supporting lake levels during periods of decline.
Construction Timeline:
The Blindman River Stabilization and Filtration Project has completed significant engineering, technical assessment, and regulatory work.
The Government of Alberta previously identified 2026 as a target for implementing the filtration system and restoring pumping operations.
As of November 2026, pumping from the Blindman River has not resumed. Although 2026 was previously identified as a target, a confirmed date for restarting pumping operations has not been announced.
Before pumping can resume, the required infrastructure work must be completed, the filtration system must be commissioned, and operational requirements must be satisfied.
Pumping also depends on sufficient water being available in the Blindman River and compliance with provincial water-management requirements.
GLWS recognizes the frustration experienced by Gull Lake residents and property owners as the lake continues to decline. We remain committed to communicating confirmed project developments and advocating for the long-term stabilization of Gull Lake.
Why This Matters:
This project represents:
-
Five decades of water management history
-
Three years of filtration research
-
Independent engineering validation
-
Multi-department provincial oversight
-
Competitive public procurement
-
An engineered plan for a modernized stabilization facility
It is the most comprehensive stabilization investment in Gull Lake since pumping began in 1976.
It protects:
-
Aquatic ecosystems
-
Shoreline integrity
-
Property values
-
Recreational use
-
The long-term sustainability of the watershed
The Next Chapter:
The Blindman River Stabilization and Filtration Project represents years of volunteer dedication, scientific investigation, engineering development, and cooperation with provincial authorities.
The project has moved beyond the initial concept and into the processes necessary to deliver a modernized pumping and filtration system.
The immediate priority is completing the remaining work required to safely restore pumping operations.
While the schedule remains uncertain, the purpose of the project has not changed.
Restoring the ability to supplement Gull Lake's water levels, while protecting its aquatic ecosystem from invasive species, remains an important part of the Society's long-term vision.
GLWS will continue working toward that objective and keeping the community informed.
How You Can Help:
The future of Gull Lake matters to everyone who lives, works, visits, or enjoys recreation in the watershed.
The Gull Lake Watershed Society is a volunteer-driven, nonprofit organization dedicated to protecting and preserving the lake for future generations.
There are several ways you can help:
Spread Awareness: Share accurate information about Gull Lake, its declining water levels, and the ongoing stabilization project with friends, neighbours, and community members.
Stay Informed: Visit www.gulllakewatershed.org regularly and follow the Gull Lake Watershed Society on Facebook for news and project developments.
Become a Member: Join the Society to stay connected with its work, receive updates, and demonstrate community support for the protection of Gull Lake.
Support the Society: Consider making a donation to help fund the Society's ongoing operations, communications, and watershed protection initiatives.
Every membership, shared update, volunteer contribution, and donation helps strengthen the community's collective voice.
Together, we can continue working toward a healthier, more sustainable future for Gull Lake.
